- Home
- Departments
- Engineering
- Capital Projects
- Town of Clayton Water Reclamation Program
Town of Clayton Water Reclamation Program
Our Water Reclamation History
The town's current wastewater treatment plant, with a history spanning 55 years, is approaching obsolescence. The limitations of the existing site, characterized by insufficient space for substantial improvements or expansions, and its inability to accommodate the rising demands of regional growth, necessitate a transformative solution.
The town's newest addition, under construction wastewater treatment facility represents a significant step forward, not only in terms of capacity but also environmental conscientiousness. This modernized facility will be equipped with state-of-the-art processes and cutting-edge equipment, tailored to align with the requirements of our growing local business sector and the expanding needs of our community.
Updates
Progress at the Sam’s Branch WRF has moved along nicely with the completion of all the round tanks (including setting the domes on top), erecting structural steel for various structures, pouring concrete for the Headworks, Bioreactor (BNR), and Influent Pump Station (IPS), and placing structural block and roof on the Administration Building. Thalle Construction, the General Contractor for the project, hit a major milestone when the IPS structure was poured and hydraulic tested to hold water. The structure passed the test and now subsequent linework and backfill of the large pit can resume. The concrete subcontractor, Donley’s, has placed 9,000 cubic yards of concrete to date, which equates to roughly 36,000,000 pounds of concrete and rebar. The Administration Building, built by Muter Construction, has progressed with the construction of the interior walls, HVAC, plumbing, and electrical systems. Once the split-faced block arrives, masons will finish the façade of the Administration Building. Roberts, the Electrical subcontractor, placed electrical duct bank sitewide and has begun terminating the conduits in the Electrical Building South (one of the two electrical buildings for the project).
In the coming months, the BNR structure, which is the largest of the project, will be completed and hydraulic tested. Following a successful test, process piping will be installed in the structure. We will see Muter continue to go vertical with structural steel and block on the two-story Thickening and Dewatering Building. Thalle pipe crews will continue to install yard piping that will convey the wastewater to the different treatment structures. Roberts will continue to place electrical duct bank and associated work in the two electrical buildings.
Updates as of November 2023
Updates as of July 2023
The ongoing transmission improvement project entails several key components. These includes the installation of a new 24-inch force main, connecting the existing Little Creek Water Reclamation Facility to the gravity discharge point on Front Street.
This endeavor involves the complex task of boring and jacking beneath critical areas such as US-70, Front Street, and the NCRR railroad tracks.
Furthermore, the project encompasses the establishment of a new gravity sewer, ranging from 24 to 48 inches in diameter, connecting Front Street to the future influent pump station for the Sam's Branch Water Reclamation Facility.
The esteemed general contractor for this project is JF Wilkerson, while the Town's designated engineer of record is Withers & Ravenel.
One of the vital project elements currently in the construction phase involves the creation of a cutting-edge pump station with an impressive capacity of 13 MGD. This station is designed to redirect flows from the established Little Creek Water Reclamation Facility to the recently developed Sam's Branch Water Reclamation Facility.
The new pump station will be equipped with state-of-the-art submersible pumps, advanced odor control systems, a reliable standby generator, and a sophisticated control building. Overseeing the construction as the general contractor is Haren, while the town's esteemed engineer of record is Withers & Ravenel.
This ECIA project component, presently in its concluding stages of design and permitting, encompasses the expansion of the Clayton-to-Raleigh pump station. This expansion is intended to facilitate the conveyance of a segment of the Town's untreated wastewater flow to the City of Raleigh's Neuse River Resource Recovery Facility.
It's noteworthy that this pump station is strategically situated in close proximity to the Sam's Branch Water Reclamation Facility site. This capacity augmentation with the City of Raleigh and effectively manage wastewater flows until the Sam's Branch WRF becomes operational. It's imperative to mention that HDR serves as the Town's designated engineer of record for this initiative.
This project component, currently under final design and permitting, includes expanding the Clayton-to-Raleigh pump station to convey a portion of the Town's raw wastewater flow to the City of Raleigh's Neuse River Resource Recovery Facility.
This pump station is located directly adjacent to the Sam's Branch WRF site. The capacity expansion will allow the Town to fully utilize its contractual treatment capacity with the City of Raleigh and manage wastewater flows until the Sam's Branch WRF comes online.
HDR is the Town's engineer of record.
- Why embark on this project?
-
The existing facility is inadequate for meeting future treatment demands, and its limited size prevents substantial improvements or expansions. Utilizing the current facility wherever feasible is a cost-effective strategy to mitigate the expenses associated with constructing new facilities.
- Will this project increase wastewater utility rates?
-
Rate adjustments are inevitable, irrespective of this project. Local and national research underscores the inescapable trend of escalating wastewater treatment costs. Neighboring communities, including Raleigh and Johnston County, are also implementing rate increases in response to the growing demand for improved wastewater services.
- How much are utility rates expected to increase?
-
Rates undergo rigorous evaluation and adjustment during the council's comprehensive budgeting process. Every endeavor is being made to minimize the necessity of rate hikes and, ideally, to implement them gradually, thus mitigating their immediate impact.
- Are developers and businesses equitably contributing to the overall cost burden?
-
Indeed, the town ensures that no customer class or type receives subsidies. While state statutes limit the fees municipalities can impose on developers, it's worth noting that we do not apply higher rates to out-of-town customers.